1. Activation planner
This block allows you to manually choose what date the next builder block should activate.
1.a Activation planned
- Activation of the next block at a specific date. Schedule this date each time
the care path has been assigned to some patient.
- Required: yes
Further in depth explanations
Activated on start of care path:
- Builder block after entry point
Offset:
- Default: none [days]
- Negative offset: date you selected minus the offset
- Positive offset: date you selected plus the offset
- Example: (in progress)
- Required: no
Delay:
- Amount of time after which the next action will be initiated
- Default: 0 [days]
- Required: yes
2. Completion
End of the care path.
To end the care path, connect the previous builder block with 'Completion'.
3. Counter
This control block is used to create returning actions (loops) in the care path.
3.a Continue loop
- The next action of the loop will be ...
3.b Counter overflow
- Maximum amount of loops (counter maximum) is reached, the next action will be ...
Further in depth explanations
Activated on start of care path:
- Builder block after entry point
Counter maximum:
- Define how many times the loop should happen
Delay:
- Amount of time after which the next action will be initiated
- Default: 0 [days]
- Required: yes